N58596 Calls Hangar, Home |
These are photos of the hangar construction over the period from when the foundation was first
poured until the Skylane was finally able to be pushed in. The photos were selected from various
photos taken at different intervals between April and September. The foundation was poured either
in late April or early May, Construction began somewhere in June/July timeframe, and the hangar
construction itself was completed in late August. It was another week or two before the taxi-way
was finally paved along with the ramp. Over Labor Day weekend, the EAA Chapter 1210 assisted in pushing the Skylane into its new home. Aside from being eaten alive by mosquitos, it all went well. |
Click on any photo to view slideshow... | |||
Construction Progress | Hangar Foundation | August Progress | Hangar Done |
Blair of Maine | Aviation Enthusiast |
Hangin at Bravo One-Niner |
Skylane Five-Niner-Six |
Hangar Construction |
Life with The Beemahs |
© BlairME.net, All Rights Reserved